| April 10 - March 11 | ||||||||||||||||||||
|
|
||||||||||||||||||||
| Our target is to register 100% of intervention orders within 5 working days of receipt of the final interlocutor | ||||||||||||||||||||
| April | May | June | July | August | September | October | November | December | January | February | March | TOTAL | ||||||||
| Welfare | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | |||||||
| Financial | 14 | 18 | 16 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 48 | |||||||
| Both | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||||||
| Total | 14 | 19 | 16 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 49 | |||||||
| No. Registered To Target | 14 | 17 | 14 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 45 | |||||||
| Actual % Achieved | 100 | 89 | 88 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 92 | |||||||